Construction Permits and Approvals in Dubai
Mobilization Permit
Mobilization Permit allows you to transfer physical and manpower resources to the construction site until the completion of the contract.
-
Building permit application
-
Appointment letter duly signed by the owner, consultant, and/or the contractor
-
Mobilization Permit Requires AED 5,000
-
Mobilization Permit for Villas requires AED 1,000 per Villa[?]
Excavation Permit
This permit is essential for ensuring that excavation activities are conducted safely, in compliance with regulations, and with proper planning.
-
Building Permit Application (in case of applying through customer service center)
-
Appointment letter signed by owner, consultant and contractor
-
Geotechnical design calculations (slope stability) for open Excavation
-
Geotechnical Model (software)
-
Excavation design drawings (as per Circular No.400)
-
NOC from relevant authorities (if applicable)
-
Excavation Design Review Checklist
-
NOC from Neighbor/Plot Owner (if Excavation in Neighbor plot)
-
Issuance or Renewal of Excavation Permit: AED 5,000
-
Issuance or Renewal of Excavation Permit for Villas AED 1,000[?]
Shoring Permit
In UAE construction, a Shoring Permit allows for the temporary support of structures during construction activities, particularly when excavations are involved.
-
Building Permit Application
-
Appointment Letter duly signed by the owner, consultant, and/or the contractor
-
Geotechnical Design Calculations
-
Geotechnical Model - software design
-
Shoring Design Drawings as per Circular No.400
-
No Objection Certificates from relevant authorities
-
Shoring Design Review Checklist
-
No Objection Certificates from the neighbor or plot owner if the excavation anchors in the neighbor’s plot
-
Peer Review of the Geotechnical Third Party Report for more than 3 basements/or special projects near the water bodies
-
Shoring Permit: AED 0.05 on Total Built-Up-Area (ft2)
-
Renewal of Shoring Permit: (AED 0.03 per ft2 on Total Built-Up-Area) x (No. of months requested for renewal) (Maximum AED 6,000 per month)[?]
Piling Permit
The permit allows the piling works to transfer the load of the structure to a required depth in deep foundations.
-
Building Permit Application
-
Appointment Letter duly signed by the owner, consultant, and/or the contractor
-
Geotechnical Design Calculations
-
Geotechnical Model - software design
-
Piling Design Drawings as per Circular No.400
-
Piling Design Review Checklist
-
Peer Review of the Geotechnical Third Party Report for building as per DM Circular No. 237
-
The piling Permit requires AED 0.1 on Total Built-Up-Area per square foot
-
Renewal of Piling Permit: (AED 0.03 per ft2 on Total Built-Up-Area) x (No. of months requested for renewal) (Maximum AED 6,000 per month)[?]
Sub-Structure Permit
Sub-Structure Permit allows contractors to proceed with the substructure or foundation work for a building project, after obtaining the necessary approvals for the structural design.
-
Building Permit Application (in case of applying through customer service center)
-
Appointment letter signed by owner, consultant and contractor
-
Sub-structure Permit is AED 0.2 per ft2 on Total Built-Up-Area
-
Renewal of Sub-structure Permit is (AED 0.03 per ft2 on Total Built-Up-Area) x (No. of months requested for renewal) (Maximum AED 6,000 per month)
Environmental and Sustainability Certifications
-
LEED and estidama. The UAE has adopted certifications like LEED (Leadership in Energy and Environmental Design) and Estidama to assess buildings based on sustainability criteria such as energy efficiency, water efficiency, site location, indoor environment quality, materials, and waste management.
-
WELL certifications. Complementing LEED, the WELL Building Standard focuses on enhancing human health and well-being within buildings by evaluating factors like air quality, water quality, nourishment, light, fitness, and comfort.
-
Green key program. The Green Key Program managed by Emirates Green Building Council offers an international eco-label for tourism facilities that demonstrate excellence in environmental responsibility and sustainable operation.
-
ESG Certification. Environmental, Social, and Governance (ESG) certification is gaining importance in the UAE as organizations commit to demonstrating their sustainability credentials.
In Dubai construction, an environmental assessment and obtaining an environmental license are mandatory requirements. Developers and contractors are obligated to undertake environmental impact assessments and adhere to stringent environmental regulations as part of the construction process.[?]
Land Demarcation Certificate
This certificate is an official document issued by relevant authorities that confirms the boundaries and dimensions of a specific piece of land.
-
Land demarcation request (in case of applying through customer service center)
-
Consultant appointment letter from the owner
-
Land demarcation request (in case of applying through customer service center)
-
Land Demarcation Request (in case of applying through customer service center)
-
As Built Survey Drawing (A3 size hard copy and AutoCAD file)
-
AED 400 per plot
Final Building Permit
Final Building Permit allows the actual construction work to commence after obtaining all the necessary approvals and clearances from the relevant authorities.
-
Building Permit Application
-
Appointment letter duly signed by the owner, consultant, and/or the contractor
-
Normal Submission is AED 1.00 per ft2 on Total Built-Up-Area (minimum AED 200). The final building permit fees will be calculated after deducting the fees which were paid previously for the Interim & Preliminary Permit except for Mobilization and Excavation Permits.
-
For Industrial plot the above fees are not to exceed AED 250,000.
-
Renewal of Final Building Permit: (AED 0.03 per ft2 on Total Built-Up-Area) x (No. of months requested for renewal) (Maximum AED 6,000 per month).
Permits and Approvals of Abu Dhabi
Building Permit
In Abu Dhabi, a Building Permit is a mandatory requirement before any construction work can commence on a new project or significant alterations to an existing building.
-
Building a new structure on an empty plot
-
Constructing a new separate building on a plot with an existing building
-
Making horizontal or vertical additions to a building
-
Making internal or external modifications to a building without adding to its size
-
Approved construction plans
-
Architectural Layout Plan
-
Architectural Plans for the Property
-
Charts and drawings
-
Electricity Scheme
-
Other Documents
-
Site Map
-
Varying cost[?]
Phased Construction Work Permit
Phased Construction Work Permit in Abu Dhabi is a permit that allows for work on a portion of a building or structure.
-
Architectural Layout Plan
-
Building plans
-
Health and Safety Policy
-
Letter of Assignment
-
Plot Survey Demarcation
-
Result of soil examination and geophysical studies
-
Site Map
-
Letter of Assignment
-
Structural calculations
-
Trade License
-
Varying cost[?]
Maintenance Permit
Maintenance Permit allows to maintain, improve, or decorate a building or shop.
-
A Pre-registered and Effective Lease Agreement
-
Architectural Layout Plan
-
Clear Photos from all the Sides of the Building
-
Contract
-
Emirates ID
-
Health and Safety Policy
-
Investment Contract
-
Legal POA in the event that the service is requested by the agent
-
Letter of Assignment
-
Pledge
-
Project Waste Management Plan as per TADWEER Form
-
Site Map
-
Trade License
-
Varying cost[?]
Demolition Permit
Demolition Permit is a critical approval required across the UAE to carry out either a complete or partial demolition of a building.
-
Application Supporting Documents
-
Approval Certificate
-
Business Plan
-
Clearance Certificate
-
Competency Certificate
-
Contract
-
DoH Letter
-
Emirates ID
-
Geo-referenced Map
-
Insurance Certificate
-
Land Delivery Registration
-
Letter from the Mortgage Entity
-
Letter of Assignment
-
Method Statement
-
Other Documents
-
Project Waste Management Plan as per TADWEER Form
-
Site Plan
-
Utility Disconnection Request
-
AED 600[?]
Permit for Boundary Wall
Permit for Boundary Wall is usually needed to build a fence or wall around a property as well as increase its height.
-
No documents are required
-
Varying cost[?]
List of Common Authority Approvals
-
Urban Planning Council or UPC approval (subjected to time limits such as Individual Projects for within 2 years and Master Plans for within 3 years)
-
Preliminary Environment Review or PER
-
License from the Abu Dhabi Environmental Agency
-
Abu Dhabi Municipality or ADM approval for Abu Dhabi City Municipality
-
Al Ain Municipality approval for Al Ain City Municipality
-
Al Dhafrah Municipality approval for Al Dhafrah Region Municipality or Western Region
-
Department of Transport Permit from the Integrated Transport Center or ITC approval associated with the access road and internal road network following the submission of a traffic effects study
-
Abu Dhabi Waste Management Centre approval on Disposal and Hazardous Waste Plan
-
Abu Dhabi Distribution Company or ADDC approval for water and electricity
-
Telecommunications Permit for Etisalat or DU
-
Abu Dhabi Sewerage Services Company or ADSSC approval for sewerage services
-
Acquire No Objection Certificate or NOC From Relevant Authorities
Obtaining Construction Permits in Other Emirates
Sharjah
Ajman
Umm Al Quwain
Ras Al Khaimah
Fujairah